1. Survey the Route Before You Mark the Floor
Confirm the navigation system
Record the vehicle model, magnetic sensor model, expected tape polarity, width range and use of separate marker pieces. A magnetic sensor designed for one field orientation may not read another tape correctly. Compatibility is a system question, not a visual check.
Walk the complete route
Mark stopping points, curves, forks, merges, charging areas, crossings and zones where staff or forklifts interact with the AGV. Götting’s installation guidance highlights route debris, obstacles, slopes and stray magnetic material as conditions that can affect travel. Inspect these before the path is fixed.
Check the real operating envelope
Test with the representative payload, wheel condition and operating direction. A route that works with an empty vehicle may behave differently under production load, especially at stops and turns.
2. Prepare and Qualify the Floor
The adhesive can only hold as well as the surface beneath it. Dust, oil and loose coatings create an interface that may fail even when the tape adhesive itself is suitable.
| Floor check | Why it matters | Practical action |
|---|---|---|
| Dryness and cleanliness | Moisture, dust and oil reduce the usable bond area. | Use the approved cleaning process and allow the floor to dry fully. |
| Coating strength | Old paint or weak epoxy may lift with the tape. | Test a small bonded area and inspect the floor layer, not only the tape. |
| Flatness and defects | Joints, cracks and sharp steps can lift edges or disturb the vehicle. | Repair the substrate or redesign the route around unsuitable sections. |
| Cleaning chemicals | Repeated chemical exposure can attack adhesive edges. | Identify detergents, scrubber method and cleaning frequency in the RFQ. |
| Cross traffic | Forklifts, pallet jacks and dragged loads can cut or displace a surface route. | Protect, reroute or evaluate an embedded section with the integrator. |
3. Install a Representative Trial Section
Do not make the easiest straight aisle your only trial. Include a typical curve, a stop or marker and at least one operational crossing. This exposes route geometry, adhesion and sensor response before the full roll is committed.
- Mark a centreline from the approved drawing.
- Check tape orientation and top-side polarity before bonding.
- Apply the strip without stretching, twisting or trapping debris.
- Use even pressure with a suitable hand roller.
- Follow the adhesive supplier’s environmental and dwell instructions.
- Run the actual AGV in both permitted directions and at controlled speed.
4. Install Straights, Curves, Forks and Markers
Long straight sections are the easy part. The quality of the project is usually decided at transitions.
Straight runs
Maintain the approved centreline and use manageable installation lengths. Press the strip progressively rather than dropping an entire run onto the floor. Avoid overlaps unless the system supplier specifically permits them.
Curves
Use the AGV manufacturer’s minimum radius. Do not force a flexible strip into a kink. If the required turn cannot be created without deformation, stop and revise the route or tape construction.
Forks, merges and markers
Roboteq’s guidance materials show that magnetic sensors can use multiple track signals and reverse-polarity pieces as location markers. That does not make every layout interchangeable. Keep a controlled drawing showing polarity, marker length and distance from each decision point.
Joints and replacements
Cut square, clean ends with no raised edge. After a local repair, repeat signal and travel checks across the joint instead of assuming the new piece is equivalent.
5. Commission the Complete Route
A route is not finished when the tape is on the floor. It is finished when the AGV has passed an agreed acceptance test.
- Verify tape detection along the full path at low speed.
- Test every curve, branch, merge, marker, stop and charging approach.
- Repeat with the representative production load.
- Observe cross-traffic, doors, cleaning equipment and nearby steel objects.
- Record any sensor adjustments and the final route drawing.
- Save a replacement-material specification and approved repair method.
If the sensor supplier provides field-visualisation or diagnostic software, use it to document signal margin instead of relying only on a successful single pass.
6. Inspect the Route as a Production Asset
Add the guide path to planned maintenance. Early action on a lifted edge is simpler than diagnosing intermittent vehicle tracking during a busy shift.
- Inspect edges, joints, curves and crossing points at a defined interval.
- Remove ferrous debris and objects that can disturb the magnetic field.
- Check for movement after aggressive floor cleaning or impact.
- Keep matching repair stock with verified polarity and dimensions.
- Recommission any modified section before returning it to normal speed.
What PAC KING Needs to Quote the Route Material
PAC KING’s current AGV navigation magnetic strip tape page lists flexible bonded-ferrite/synthetic-rubber construction, rubber adhesive, adhesive and non-adhesive options, and published formats of 1.2 mm × 50 mm × 25 m and 1.2 mm × 30 mm × 50 m.
For an installation-matched quote, also send the sensor model, polarity, total route length, curves and branches, floor coating, crossing traffic, installation method, operating environment and required delivery format. Final values should follow the quoted model and current TDS.